Introduction
The Warren County Bikeway Extends from the southernmost point of Lake George, by the Million Dollar Beach, and ends in Glens Falls, where it connects to the Feeder Canal Park Heritage Trail. The trail experiences much elevation change along with varying road types and surface types, as well as multiple possible routes. 

Objectives
• Using GPS Points, generate an accurate map of the bike trail and surrounding features, showing major roads and elevation changed
• Parking lots with access to the trail will be mapped
• Mile markers will be shown

Methodology
Since the snow will have to melt in order to fully complete this project first I will map out parking lot locations for bikers. Once the trails become rideable I will go on the bike trail, taking GPS points. I will note which points are mile markers and also when road type and surface type changes so I can mark them on the map. This may take multiple days on the trail to complete to get every route and ensure accuracy.  After all the data is collected it will be entered into an excel table and imported into ArcMap in order to create a map using the attributes within the table.  To show elevation change I will also use the profile tool with a Digital Elevation Model.
  
Data Sources 
Streets Basemap
Digital Elevation Model
New York state water body shapefile
Streets shapefile
Table of all necessary GPS Points taken
Town and County Line shapefiles

Deliverables
• A map showing the trail over a streets base map with roads, along with points showing parking, waterbodies, and mile markers.  This will be 8.5x11 in. so they can be printed and carried easily.   
• A second map will be available showing elevation change which will also be 8.5x11

Weekly Work Plan
March 15-22- Begin plugging in data sources into map to prepare for when GPS data points are ready to be entered.  

March 22-29- Begin taking points of parking lot locations

March 29-April 5- Put points of parking lots into maps, also if snow is melted, begin taking 
points on trail.

April 5-19- Continue riding trail, collecting necessary data.

April 19-May 3- Make table of data and import into ArcMap.  Create Draft Map for revision. Add all required layers and export interactive map to ArcGIS online.

May 3-10- Extra time if necessary if snow pushed mapping back,